The short answer
- RAMS stands for risk assessment and method statement, a pair of documents in which the risk assessment identifies hazards and controls and the method statement sets out how a task will be done safely, step by step.
- Employers must assess risks under the Management of Health and Safety at Work Regulations 1999 and, with five or more employees, record the significant findings; method statements are common practice and often required by contract.
- Digital RAMS make it easy to brief the current version on site, capture each worker’s sign-off with a name and time, and show an auditor who saw which version.
Digital RAMS are risk assessments and method statements written, briefed and signed on a phone or tablet instead of on paper. RAMS stands for risk assessment and method statement, where the risk assessment identifies hazards and how they are controlled, and the method statement sets out how a particular task will be done safely, step by step. Done well on a phone, RAMS reach the people doing the work in their current version, and the sign-off records who was briefed, on what and when.
What RAMS are
RAMS is an industry term for two documents that are usually prepared together for a task or a package of work.
- A risk assessment identifies the hazards in the work, who could be harmed and how, how serious the risk is, and the precautions that control it.
- A method statement describes how the task will be carried out, including the sequence of work, the people and competences needed, the plant and equipment, the access arrangements, and how the controls from the risk assessment apply at each step.
Principal contractors commonly ask each subcontractor to submit RAMS for review before starting a package, such as roofing, groundworks or steel erection, and then to brief them to the operatives who will do the work.
What the law requires
The legal duty is to assess risk. Regulation 3 of the Management of Health and Safety at Work Regulations 1999 requires every employer to make a suitable and sufficient assessment of the risks to its employees and to others affected by its work. Employers with five or more employees must record the significant findings. HSE’s guidance describes the process as identifying hazards, assessing the risks, controlling them, recording the findings and reviewing the controls.
No law names a method statement as a required document. It is a well-established way of showing how risks will be controlled for a complex or high-risk task, HSE guidance refers to method statements for some types of work, and principal contractors and clients often require them in their contracts. In practice, a builder working for a main contractor will rarely start work without accepted RAMS.
Where RAMS sit alongside CDM 2015
The Construction (Design and Management) Regulations 2015 set out duties for clients, designers, principal designers, principal contractors and contractors on construction projects. Contractors must plan, manage and monitor their work so that, so far as is reasonably practicable, it is carried out without risks to health and safety. Every project needs a construction phase plan, drawn up by the principal contractor or, where there is only one contractor, by that contractor. Contractors must give workers under their control appropriate supervision, instructions and information, including a suitable site induction.
RAMS are one of the main ways contractors meet those duties for specific tasks. The construction phase plan sets out the arrangements for the project as a whole. The RAMS for each package show how that package will be done safely, and the briefing record shows that the information reached the people doing it. For how this and other rules shape construction software, see the unglamorous half of construction software.
Briefing and sign-off on site
Paper RAMS tend to fail in the same ways. A long generic document is printed, signed by a supervisor and filed in the site cabin. Operatives sign a sheet they haven’t read. The method changes after a design revision, and the old copy is still in the folder. When something goes wrong, nobody can show which version was briefed or who was there.
Digital RAMS can’t fix a poor assessment. They make the good habits easier to repeat every time, with the right version briefed to the right people and a record that can be found later.
How to run a briefing on a phone
A RAMS briefing is the conversation in which a supervisor explains the method and the controls to the operatives before they start. A signature is evidence that the briefing happened, and the briefing itself is what keeps people safe. A phone helps with both.
- Open the current version on site. The supervisor opens the RAMS for the task on a phone or tablet, and the app shows the revision number and approval status.
- Brief it in person. Walk through the sequence, the hazards and the controls, at the place where the work will happen if possible.
- Check understanding. Ask operatives to explain the key controls back, and use pictures or a translated summary where English isn’t someone’s first language.
- Capture each sign-off. Each operative confirms on the device, and the record stores their name, the time, the RAMS revision and, where useful, the location.
- Brief late starters. Anyone who joins later is briefed before starting, and their sign-off is added to the same record.
- Stop and re-brief when things change. If the method has to change on site, the work stops, the RAMS are revised, and the new version is briefed.
An electronic sign-off with a name, date, time and document version is generally accepted as a record of a briefing. Check what your clients and principal contractors require, as some specify their own forms or systems.
Version control
Every RAMS document should have a revision number, a date, an author and an approver. When it changes, the old version is kept, marked as superseded, and never shown as current. A digital system makes this automatic, and it links each sign-off to the exact revision that was briefed.
| Event | What should happen | What the record shows |
|---|---|---|
| First issue | Written, reviewed and approved | Revision A, author, approver, date |
| Submitted to principal contractor | Accepted, or returned with comments | Status and comments with dates |
| Briefed on site | Operatives briefed, then sign | Names, times and the revision briefed |
| Design or method change | Revised, re-approved, old version superseded | Revision B and the reason for the change |
| Re-briefed | Affected operatives briefed on the change | New sign-offs against revision B |
| Incident or near miss | Controls reviewed | Review date and outcome |
Audits and inspections
When a client, a principal contractor or an HSE inspector asks about a task, the questions are predictable. Was the work assessed? Were the controls appropriate? Did the people doing it know about them? A digital record answers the last question directly, by showing the revision, the briefing and every sign-off with times. It also makes internal audits quicker, because a manager can see across all jobs which RAMS are out of date, waiting for approval or missing sign-offs.
Keep the RAMS with the job they belong to. When they live in the same record as the schedule, the subcontractor details and the site diary, it is easy to see which packages were on site on a given day and which RAMS covered them.
What to look for in a digital RAMS tool
- It works offline, because briefings happen in places without signal.
- It shows revision and approval status clearly on every screen.
- It captures sign-offs against a specific revision, with name and time.
- It builds RAMS from your own templates, which you then edit for the task and site.
- It exports a clean PDF for principal contractors who ask for one.
- It keeps superseded versions and the history of changes.
In Estimark, health and safety paperwork sits in the same job record as estimates, scheduling and site diaries, the app works offline on site, and it includes a field worker mode.
Questions people ask
Are RAMS a legal requirement?
Risk assessment is a legal requirement under the Management of Health and Safety at Work Regulations 1999, and employers with five or more employees must record the significant findings. No law names a method statement as a required document, though principal contractors and clients commonly require RAMS before work starts. CDM 2015 also requires work to be planned and workers to receive appropriate supervision, instructions and information.
What is the difference between a risk assessment and a method statement?
A risk assessment identifies hazards, who could be harmed and the controls needed. A method statement describes how a specific task will be carried out safely, step by step, applying those controls. Together they are known as RAMS.
Can operatives sign RAMS on their phones?
Operatives can confirm a RAMS briefing on a phone or tablet, and the record should store their name, the time and the revision briefed. Many contractors use the supervisor’s device so the sign-off happens at the briefing itself. Check whether your principal contractor has its own requirements.
How often should RAMS be reviewed?
RAMS should be reviewed whenever the work, the site conditions, the design or the people change, and after any incident or near miss. A risk assessment must be reviewed if there is reason to suspect it is no longer valid or if there has been a significant change. Each review should produce a new revision with a date and a reason.